FCC Orders Nai Gaj Dam Contractor to Complete Work Under Original Contract Terms — image representing a Pakistan hydropower dam and electricity generation
PolicyDevelopingAI

FCC Orders Nai Gaj Dam Contractor to Complete Work Under Original Contract Terms

Pakistan's Federal Constitutional Court has overturned Sindh High Court orders that allowed the Nai Gaj Dam contractor to claim price escalation beyond the original contract, directing completion under the original agreement and the 2021 MoU. The FCC also barred all further court intervention in the project's execution until the dam is finished.

PowerPost AI Bureau · Reviewed by Editorial Team3 min read0 views

Pakistan's Federal Constitutional Court (FCC) on Monday set aside multiple orders by the Sindh High Court (SHC) that had allowed the contractor on the long-delayed Nai Gaj Dam to claim price escalation beyond the original contract, directing that all remaining work be completed strictly under the original agreement, the arbitral award, and the September 21, 2021 memorandum of understanding (MoU). A two-judge bench — headed by Chief Justice Aminuddin Khan and comprising Justice Ali Baqar Najafi — also barred all courts from intervening in the project's execution until the dam is complete.

Background: A Project Stuck in Legal Limbo

The Nai Gaj Dam is a WAPDA (Water and Power Development Authority) multipurpose project in Sindh, designed to provide both irrigation water for the province's agricultural land and hydroelectric power generation. The project has been mired in delays for years. The contractor, NEIE SMADB-LILLEY-RMS Karachi, had obtained SHC rulings permitting cost escalation beyond the original agreed terms. WAPDA contested those claims, and the dispute eventually reached the FCC through a set of appeals.

An earlier arbitral award and the September 2021 MoU had both attempted to create a framework for resuming construction. The SHC judgements, however, granted the contractor entitlements that extended beyond those frameworks — entitlements the FCC has now struck down.

What the 21-Page FCC Judgement Directs

  • The contractor must complete all remaining works strictly under the original contract, the arbitral award, and the September 21, 2021 MoU — not under the SHC-expanded terms.
  • WAPDA must consider and respond to any contractor request to resume work within 15 days of receiving it, provided the contractor unequivocally commits to the original terms.
  • WAPDA may grant a reasonable extension of the construction period, but only under the contractual provisions that already govern such extensions.
  • Any extension of time will not entitle the contractor to additional price escalation payments.
  • No court — including the SHC — may intervene in the project's execution until the dam is complete, except through the dispute resolution mechanism set out in the original contract.

The court stated in its judgement that the purpose of the bar on judicial intervention is "to prevent further litigation from impeding the execution of an important public infrastructure project."

Why This Matters for Pakistan's Energy Sector

WAPDA manages a significant share of Pakistan's hydroelectric generation capacity. The Nai Gaj Dam's hydroelectric component, once operational, would add generation to a national grid that is heavily weighted toward expensive oil- and gas-fired thermal plants. Those thermal plants are the primary reason consumers see fuel cost adjustment (FCA) charges on every electricity bill — additional per-unit costs that fluctuate with global fuel prices and that have pushed household bills sharply higher over the past three years.

The project's location in Sindh also makes its completion particularly relevant to HESCO (Hyderabad Electric Supply Company), the distribution company (DISCO) serving that part of the province. HESCO's service territory contends with chronic supply shortfalls and infrastructure deficits; additional hydro capacity in the region would improve both supply reliability and long-term cost pressures for consumers there.

Frequently Asked

Questions about this story

  • What is the Nai Gaj Dam and why has it been delayed for so long?
    The Nai Gaj Dam is a WAPDA multipurpose project in Sindh designed to deliver irrigation water and hydroelectric power generation. It has been delayed for years due to a prolonged dispute between WAPDA and the contractor, NEIE SMADB-LILLEY-RMS Karachi, over price escalation claims that escalated into Sindh High Court litigation.
  • What exactly did the Federal Constitutional Court decide about the Nai Gaj Dam dispute?
    The FCC set aside Sindh High Court orders that had allowed the contractor to claim price escalation beyond the original contract terms. The court directed the contractor to complete all remaining work under the original agreement, the arbitral award, and the September 21, 2021 MoU, and ruled that any time extension granted by WAPDA will not entitle the contractor to additional escalation payments.
  • Can the contractor or WAPDA take the Nai Gaj Dam dispute back to court while construction is ongoing?
    No. The FCC has barred all judicial proceedings and court intervention — including by the Sindh High Court — until the dam is fully complete. Any disputes that arise during construction must be resolved through the dispute resolution mechanism already set out in the original contract.
  • Will completing Nai Gaj Dam reduce electricity bills or load shedding for Pakistani consumers?
    Not immediately, and the FCC ruling itself changes no tariff or charge. However, once the dam's hydroelectric component is operational, it would add lower-cost hydro generation to the national grid, which over time reduces the fuel cost adjustment (FCA) component consumers pay on their monthly electricity bills — most directly benefiting HESCO consumers in Sindh.
  • How long does WAPDA have to respond if the contractor agrees to resume Nai Gaj Dam construction?
    The FCC directed WAPDA to consider and decide on any contractor request to resume work within 15 days of receiving it, provided the contractor unequivocally commits to completing the project strictly under the original contractual terms.

Free Newsletter

Get Pakistan's Energy Week in 3 Minutes

NEPRA decisions, tariff moves, solar updates, and load shedding news — one short email every week. No spam.

One email per week · Unsubscribe anytime · No spam

RelatedMore from policy
World Bank Approves $375.9 Million to Upgrade Pakistan's Power Transmission Grid — image representing Pakistan solar energy and net-metering coverage
PolicyAIJul 11, 2026

World Bank Approves $375.9 Million to Upgrade Pakistan's Power Transmission Grid

The World Bank has approved $375.9 million in financing for Pakistan's Grid Stability Enhancement Project, the first phase of a 10-year programme to modernise the national transmission network and cut power outages. The project will unlock 640MW of currently curtailed wind energy and enable the full use of 1,840MW of southern Pakistan's wind capacity, aiming to structurally reduce fuel costs on household electricity bills.

3 min readNEW
Senate Committee Unanimously Demands FIA and NAB Probe Into Foreign-Funded Power Projects — image representing Pakistan energy policy and government coverage
PolicyAIJul 4, 2026

Senate Committee Unanimously Demands FIA and NAB Probe Into Foreign-Funded Power Projects

Pakistan's Senate Standing Committee on Economic Affairs Division has unanimously voted to brief the Prime Minister and formally request FIA and NAB investigations into alleged irregularities in foreign-funded power sector projects. The move came after the Economic Affairs Division said it cannot order inquiries into another ministry's affairs, prompting senators to accuse officials of obstructing parliamentary oversight.

3 min read
Iranian Oil for Pakistan: Why the Real Opportunity Lies in Refining Capacity, Not Just Discounted Imports — image representing Pakistan energy policy and government coverage
PolicyAIJul 1, 2026

Iranian Oil for Pakistan: Why the Real Opportunity Lies in Refining Capacity, Not Just Discounted Imports

The recurring conversation about discounted Iranian crude for Pakistan frames the opportunity too narrowly. Pakistan's structural import problem is dominated by refined products, not crude — so the strategic prize is investing in domestic refining capacity that captures the crack spread, not just sourcing cheaper barrels.

4 min read