Sindh Engro Coal Mining Company's Thar Block-II mine has expanded to 11.2 million tonnes per year after its Phase-III inauguration on 14 November 2026. The addition raises Thar-linked electricity generation capacity to 1,980 MW and is projected to save Rs. 15 billion annually in power generation costs.

PowerPost AI Bureau · Reviewed by Editorial Team3 min read

Sindh Engro Coal Mining Company's (SECMC) Thar Block-II coal mine can now produce 11.2 million tonnes of coal per year after its Phase-III expansion was inaugurated on 14 November 2026 — a leap from 7.6 million tonnes per annum (MTPA) that will raise total electricity generation backed by the mine from 1,320 megawatts to 1,980 megawatts. Pakistan Peoples Party Chairman Bilawal Bhutto-Zardari opened the expansion and the country's first coal drying unit at a ceremony in Tharparkar, Sindh.

Seven Years, Three Expansions

SECMC began commercial operations at Thar Block-II in 2019 with an initial capacity of just 3.8 MTPA. A Phase-II expansion completed in 2022 doubled output to 7.6 MTPA. The latest Phase-III addition puts 3.6 MTPA more on top of that, making 11.2 MTPA in total — the mine's third capacity increase in seven years. Notably, the entire Phase-III programme was funded through 100 percent self-financing, with no fresh external debt raised for the expansion.

SECMC Chief Executive Officer Amir Iqbal credited public-private partnerships and local engineering expertise for the pace of development. Sindh Chief Minister Syed Murad Ali Shah acknowledged the contribution of engineers, workers, and stakeholders in advancing the project.

Lucky Electric and the Power Generation Picture

The additional 3.6 MTPA of coal output will feed Lucky Electric Power Company's 660-megawatt power plant, the incremental generation unit linked to the expanded mine. That pushes total installed electricity generation capacity supplied from Thar Block-II coal to 1,980 MW, up from 1,320 MW previously. Officials at the ceremony said this output is enough to supply approximately 4.5 million households daily.

Mine-mouth generation cost at Thar Block-II stands at around $3.75 per MMBtu (≈ Rs. 1,050 at current interbank rates), which SECMC positions as a competitive alternative to imported coal. The expansion is projected to save approximately Rs. 15 billion per year in power generation costs and $220 million (≈ Rs. 61.6 billion) in annual foreign exchange outflows. Since SECMC began operations in 2019, cumulative foreign exchange savings have already exceeded $1.7 billion (≈ Rs. 476 billion).

Source: EnggPost

Frequently Asked

Questions about this story

  • How much will the Thar Block-II Phase-III expansion save in annual power generation costs?
    The expansion is expected to save approximately Rs. 15 billion per year in power generation costs and $220 million (roughly Rs. 61.6 billion) in annual foreign exchange outflows, according to officials at the inauguration ceremony.
  • How many households can the expanded Thar Block-II coal capacity power each day?
    Officials stated at the inauguration that the expanded capacity — now supporting 1,980 MW of electricity generation — is sufficient to supply approximately 4.5 million households daily.
  • What is the mine-mouth electricity generation cost from Thar Block-II coal?
    The mine-mouth generation cost at Thar Block-II stands at around $3.75 per MMBtu, which SECMC describes as a competitive alternative to imported coal used by other power plants in Pakistan.