The short version: since 9 February 2026, new rooftop solar connections in Pakistan are on net billing, not net metering. You pay the normal tariff for grid units and are credited a much lower rate for the units you export. If you already had net metering, you keep your old terms until your agreement runs out.

What changed in 2026

NEPRA, the power regulator, notified the NEPRA (Prosumer) Regulations, 2026 on 9 February 2026. They replaced the 2015 distributed generation and net metering regulations. A “prosumer” is a consumer who also generates power, in practice a home, shop, farm or factory with solar panels connected to the grid.

The first version would have moved existing consumers to the new system as well. An amendment on 2 April 2026 reversed that: anyone with a valid agreement under the 2015 rules stays on the old rate and method until that agreement expires.

New connections and existing ones compared

New connections (net billing)Existing net metering
How you are billedNet billing: imports and exports are priced separately.Net metering, on the old rate and method, until the agreement expires.
Units you take from the gridNormal tariff for your slab or time-of-use rate.Normal tariff for your slab or time-of-use rate.
Units you send to the gridNational average energy purchase price. NEPRA used Rs. 8.13 per unit for April to June 2026.The old net metering rate. NEPRA used Rs. 25.32 per unit for April to June 2026.
If your exports are worth more than your importsThe balance is credited to the next bill or paid to you each quarter.As set out in your existing agreement.
Length of agreementFive years from commissioning, renewable for five years at a time by mutual consent.Runs to its original expiry date. Any extension is on the 2026 terms.

The export rates above are the ones NEPRA used in its September 2026 quarterly adjustment. News reports have quoted slightly different figures, about Rs. 10 to 11 for net billing and Rs. 26 to 27 for net metering. Both follow the power purchase price, which NEPRA is reviewing for 2027, so expect them to move. NEPRA can also revise the export rate during an agreement.

Existing consumers, take note: the protection ends if you materially modify the system so that its maximum output changes. Adding panels or a bigger inverter can move you to net billing.

Who can apply, and how big the system can be

  • You need a three-phase connection (400 V or 11 kV). Homes, shops, industry, farms and bulk-supply consumers are eligible.
  • Solar, wind and biogas systems are covered.
  • The system must be between 1 kW and 1 MW and no larger than your sanctioned load.
  • The company must not accept new applications once generation on your distribution transformer reaches 80% of its rated capacity.
  • Systems of 250 kW or more need a load-flow study.

Approval and fees

  • Up to 25 kW: your distribution company approves it. NEPRA's concurrence is not needed (amendment of 6 August 2026).
  • Above 25 kW: NEPRA's concurrence is needed. The application fee is a one-time, non-refundable Rs. 1,000 per kW.
  • You pay for the interconnection and the meter.
  • The company must give you the application forms free of charge.

The steps, and the time limits in the rules

StepLimit in the regulations
Distribution company acknowledges your application5 working days
Initial review of the application15 working days
Agreement signed7 working days
Connection charge estimate issued7 working days
You pay the estimate7 working days
Meter installed and system commissioned15 working days

These are the maximum times the regulations allow for each step. How long your own distribution company takes can differ. In Karachi, K-Electric takes applications through an online portal and asks for a solar vendor certified by the Private Power and Infrastructure Board.

What to watch next

  • NEPRA's decision on the power purchase price for 2027, which would reset both export rates.
  • Any further amendment to the regulations. We found none pending when this page was last updated.
  • A Lahore High Court petition against the regulations was disposed of in February 2026 after the petitioner did not pursue it.

Costing a system? See solar panel and inverter prices in Pakistan. To see what a grid unit costs you, see how to read your electricity bill.

Sources

Frequently asked

Net metering & prosumer rules 2026: FAQs

  • Has net metering ended in Pakistan?
    For new connections, yes. Since 9 February 2026 new rooftop solar connections are on net billing under the NEPRA (Prosumer) Regulations, 2026, which replaced the 2015 net metering regulations. Consumers who already had a valid net metering agreement keep the old terms until that agreement expires.
  • What is the difference between net metering and net billing?
    Under net metering, the units you export are set against the units you import, so an exported unit is worth roughly what a grid unit costs you. Under net billing the two are priced separately: you pay the normal tariff for every unit you take from the grid, and you are credited a lower rate, the national average energy purchase price, for every unit you send to it.
  • What is the solar buyback rate in Pakistan in 2026?
    In its September 2026 notification NEPRA valued exported units for April to June 2026 at Rs. 8.13 per unit for net-billing consumers and Rs. 25.32 per unit for consumers still on net metering. Press reports have quoted about Rs. 10 to 11 and Rs. 26 to 27. The rates follow the power purchase price and can change when it is reset.
  • I already have net metering. Does the new rule change my bill?
    Not while your current agreement is valid. An April 2026 amendment says existing net-metered consumers stay on the old rate and method until their agreement expires. The protection ends if you materially change the system so that its maximum output changes, and any extension after expiry is on the new net billing terms.
  • How big a solar system can I install under the 2026 rules?
    The system may not be larger than your sanctioned load, within a range of 1 kW to 1 MW, and you need a three-phase connection. The distribution company must refuse new applications once solar and other distributed generation on your transformer reaches 80% of its capacity.
  • Do I need NEPRA's approval for a home solar system?
    Not for systems of 25 kW or below. Under an August 2026 amendment those need only the distribution company's approval. Larger systems need NEPRA's concurrence, for which the application fee is Rs. 1,000 per kW.