Net metering and prosumer rules in Pakistan (2026)
How rooftop solar is billed in Pakistan in 2026: net metering versus net billing, buyback rates, system size limits, existing versus new connections and how to apply.
Last updated:
By the PowerPost editorial team
The short version: since 9 February 2026, new rooftop solar connections in Pakistan are on net billing, not net metering. You pay the normal tariff for grid units and are credited a much lower rate for the units you export. If you already had net metering, you keep your old terms until your agreement runs out.
What changed in 2026
NEPRA, the power regulator, notified the NEPRA (Prosumer) Regulations, 2026 on 9 February 2026. They replaced the 2015 distributed generation and net metering regulations. A “prosumer” is a consumer who also generates power, in practice a home, shop, farm or factory with solar panels connected to the grid.
The first version would have moved existing consumers to the new system as well. An amendment on 2 April 2026 reversed that: anyone with a valid agreement under the 2015 rules stays on the old rate and method until that agreement expires.
New connections and existing ones compared
| New connections (net billing) | Existing net metering | |
|---|---|---|
| How you are billed | Net billing: imports and exports are priced separately. | Net metering, on the old rate and method, until the agreement expires. |
| Units you take from the grid | Normal tariff for your slab or time-of-use rate. | Normal tariff for your slab or time-of-use rate. |
| Units you send to the grid | National average energy purchase price. NEPRA used Rs. 8.13 per unit for April to June 2026. | The old net metering rate. NEPRA used Rs. 25.32 per unit for April to June 2026. |
| If your exports are worth more than your imports | The balance is credited to the next bill or paid to you each quarter. | As set out in your existing agreement. |
| Length of agreement | Five years from commissioning, renewable for five years at a time by mutual consent. | Runs to its original expiry date. Any extension is on the 2026 terms. |
The export rates above are the ones NEPRA used in its September 2026 quarterly adjustment. News reports have quoted slightly different figures, about Rs. 10 to 11 for net billing and Rs. 26 to 27 for net metering. Both follow the power purchase price, which NEPRA is reviewing for 2027, so expect them to move. NEPRA can also revise the export rate during an agreement.
Existing consumers, take note: the protection ends if you materially modify the system so that its maximum output changes. Adding panels or a bigger inverter can move you to net billing.
Who can apply, and how big the system can be
- You need a three-phase connection (400 V or 11 kV). Homes, shops, industry, farms and bulk-supply consumers are eligible.
- Solar, wind and biogas systems are covered.
- The system must be between 1 kW and 1 MW and no larger than your sanctioned load.
- The company must not accept new applications once generation on your distribution transformer reaches 80% of its rated capacity.
- Systems of 250 kW or more need a load-flow study.
Approval and fees
- Up to 25 kW: your distribution company approves it. NEPRA's concurrence is not needed (amendment of 6 August 2026).
- Above 25 kW: NEPRA's concurrence is needed. The application fee is a one-time, non-refundable Rs. 1,000 per kW.
- You pay for the interconnection and the meter.
- The company must give you the application forms free of charge.
The steps, and the time limits in the rules
| Step | Limit in the regulations |
|---|---|
| Distribution company acknowledges your application | 5 working days |
| Initial review of the application | 15 working days |
| Agreement signed | 7 working days |
| Connection charge estimate issued | 7 working days |
| You pay the estimate | 7 working days |
| Meter installed and system commissioned | 15 working days |
These are the maximum times the regulations allow for each step. How long your own distribution company takes can differ. In Karachi, K-Electric takes applications through an online portal and asks for a solar vendor certified by the Private Power and Infrastructure Board.
What to watch next
- NEPRA's decision on the power purchase price for 2027, which would reset both export rates.
- Any further amendment to the regulations. We found none pending when this page was last updated.
- A Lahore High Court petition against the regulations was disposed of in February 2026 after the petitioner did not pursue it.
Costing a system? See solar panel and inverter prices in Pakistan. To see what a grid unit costs you, see how to read your electricity bill.
Sources
- NEPRA (Prosumer) Regulations, 2026, S.R.O. 251(I)/2026 (9 February 2026) — the rules for new solar connections
- NEPRA amendment S.R.O. 547(I)/2026 (2 April 2026) — protection for existing net-metered consumers
- NEPRA amendment S.R.O. 1330(I)/2026 (6 August 2026) — approval of systems up to 25 kW
- NEPRA S.R.O. 1501(I)/2026 (7 September 2026) — quarterly adjustment for September to November 2026; export rates for solar prosumers
- K-Electric: Net Billing — applying in Karachi
- The Express Tribune (25 February 2026) — Lahore High Court petition