HNDS Energy Files NEPRA Tariff Modification Petition
HNDS Energy Limited filed a Tariff Modification Petition with NEPRA in August 2026 for a solar project of up to 50 MWp. The company argues it cannot recover Interest During Construction and Return on Equity During Construction costs because land disputes in Sindh delayed its construction start by more than 16 months after Financial Close.
HNDS Energy Limited, a solar independent power producer (IPP) licensed for a project of up to 50 megawatts-peak (MWp), filed a Tariff Modification Petition with NEPRA (the National Electric Power Regulatory Authority) on 4 August 2026, seeking a change to how the construction period in its approved tariff is measured — a change the company says is necessary to recover costs the original tariff determination was designed to cover.
The Construction Delay at the Heart of the Petition
HNDS Energy's current reference tariff — determined under NEPRA order reference NEPRA/R/TRF-481/HPPL-2019/6094-6096 dated 21 February 2020 — includes provision for the recovery of Interest During Construction (IDC) and Return on Equity During Construction (ROEDC). Both are standard costs recognised in Pakistani IPP tariff frameworks to compensate developers for capital tied up before a plant begins generating revenue.
The problem, according to HNDS, is that the approved tariff measures the 10-month construction period from the date of Financial Close. The company achieved Financial Close on 19 February 2021. However, the actual Construction Start Date was not reached until 14 June 2022 — more than 16 months later — because of land demarcation problems, revised project coordinates, and local land-ownership disputes involving the Government of Sindh.
By the time construction could physically begin, the 10-month window had already expired under the existing tariff clock. HNDS argues this means no meaningful IDC or ROEDC draw-down was possible, leaving the company unable to recover costs the original determination had explicitly allowed. The petition calls on NEPRA to recognise the Construction Start Date — rather than Financial Close — as the reference point for the construction period, and cites precedents in which NEPRA has previously granted similar relief to other projects.
Filing Details and Regulatory Status
The petition was assigned letter reference 1247-LET-HNDS-NEPR-6499 and received by NEPRA on 5 August 2026. It was submitted in triplicate by Jawad Ali, Country Manager, who was authorised by a certified board resolution to act as the company's representative. A completed examination checklist was submitted separately on 10 August 2026 under letter reference 1247-LET-HNDS-NEPR-6505.
The filing fee paid was PKR 747,777, corresponding to the NEPRA schedule category for generation licensees with projects of more than 20 MW up to 50 MW. NEPRA has published the petition as an admission notice, indicating it has entered the formal regulatory review process. The generation licence carried a first modification dated 28 September 2023 and an expiry date of 29 April 2048.
- Petition filed: 4 August 2026 (received by NEPRA: 5 August 2026)
- Checklist submitted: 10 August 2026
- Filing fee: PKR 747,777
- Project capacity: up to 50 MWp solar
- Financial Close achieved: 19 February 2021
- Construction Start Date achieved: 14 June 2022
Source: NEPRA
Frequently Asked
Questions about this story
What is HNDS Energy Limited asking NEPRA to change in its tariff?
HNDS Energy is asking NEPRA to measure the approved 10-month construction period from the actual Construction Start Date of 14 June 2022, rather than from the Financial Close date of 19 February 2021. This would allow the company to recover Interest During Construction (IDC) and Return on Equity During Construction (ROEDC) costs that its original tariff determination was designed to cover.Why was construction on the HNDS Energy solar project delayed?
HNDS Energy attributes the delay to land demarcation issues, revised project coordinates, and local land-ownership disputes involving the Government of Sindh. As a result, the Construction Start Date of 14 June 2022 came more than 16 months after Financial Close was achieved on 19 February 2021.How much did HNDS Energy pay to file this tariff modification petition with NEPRA?
HNDS Energy paid a filing fee of PKR 747,777 by pay order. This fee corresponds to the NEPRA schedule category for generation licensees operating projects of more than 20 MW up to 50 MW.