Rock Collapse Floods Tunnel at 1,530 MW Tarbela T5 Project
A rock-mass collapse on November 9, 2026 flooded the connecting tunnel and powerhouse area of the Tarbela 5th Extension Hydropower Project, with all workers evacuated safely. The 1,530 MW project, whose estimated cost has risen from Rs. 82 billion to Rs. 317 billion after a previous cofferdam failure, now faces fresh questions over its revised June 2028 completion target.
A rock-mass collapse on November 9, 2026, allowed a large volume of water to flood a connecting tunnel and the under-construction powerhouse area at the Tarbela 5th Extension Hydropower Project (T5), adding to a string of setbacks at a project whose estimated cost has already ballooned from Rs. 82 billion to Rs. 317 billion. All workers were evacuated safely, and no casualties were reported. The Water and Power Development Authority (WAPDA) confirmed that the main Tarbela Dam and its critical structures were not under threat.
What Happened on November 9
The incident occurred during excavation of the second bench of the connecting tunnel at the T5 construction site. A weak section of rock mass gave way, allowing water from the intake pit to rush into the connecting tunnel and the adjacent powerhouse cavity. WAPDA declared an emergency, suspended all construction activities and immediately evacuated workers from the affected areas.
Initial reports circulated suggesting the project's main tunnel had collapsed. WAPDA subsequently clarified that the failure was confined to the rock section in the connecting tunnel. In its initial assessment, the authority indicated that the main tunnel, powerhouse structure, tailrace culvert and switchyard had not sustained structural damage. WAPDA Chairman Lieutenant General (Retd) Muhammad Saeed visited the site on November 9 and 10 and ordered a departmental inquiry. The Ministry of Water Resources received an initial assessment from WAPDA on November 10.
Restoration Work and Ministerial Visit
Recovery teams gave immediate priority to stopping the water inflow and draining affected zones. WAPDA reported that water accumulated in the intake pit was completely drained shortly after the incident. Heavy-duty pumping equipment was deployed to begin dewatering the under-construction powerhouse.
By November 13, concrete pouring was underway to fill the crater left by the rock collapse and stabilise the opening. Project officials estimated the concrete work and powerhouse dewatering could take approximately one week, though this was an anticipated timeline rather than a confirmed completion date.
Federal Minister for Water Resources Mian Muhammad Mueen Wattoo visited the site on November 15, reviewed restoration progress and directed teams to accelerate work while maintaining safety and quality standards. He also instructed WAPDA project management, consultants and contractors to prepare contingency arrangements to minimise further delay in the project's completion.
Engineering specialists cited in the Engineering Review report draw an important distinction: draining water and filling a crater do not, by themselves, confirm that the surrounding rock mass has regained the structural stability required for construction to safely resume. An independent geological and engineering assessment will be necessary before full construction activities restart.
Accountability and the Project's Troubled History
T5 carries a difficult record. In August 2025, a cofferdam at the site collapsed. A government-constituted inquiry committee reporting in July 2026 held WAPDA, the contractor and the consultant jointly responsible for that earlier failure, citing unauthorised post-contract design changes, inadequate technical scrutiny and failures in supervision and approval processes. The contractors involved included Power Construction Corporation of China, HEI and HEM; the consultancy arrangements involved Mott MacDonald and associated partners.
Those findings relate specifically to the August 2025 cofferdam collapse, not to the November 2026 rock failure. No publicly available inquiry finding had established responsibility for the latest incident at the time of reporting. The departmental inquiry ordered by WAPDA Chairman Saeed must determine whether the rock failure was an unforeseen geological event or whether deficiencies in site investigation, excavation methodology, rock support, drainage, monitoring or engineering supervision contributed to it. It must also examine whether the contractor followed approved construction procedures and whether the consultant and WAPDA exercised adequate oversight.
T5 has an installed generation capacity of 1,530 megawatts (MW) and is being developed with financial assistance from the World Bank and the Asian Infrastructure Investment Bank (AIIB). Following the August 2025 cofferdam collapse, the project's estimated cost rose from approximately Rs. 82 billion to Rs. 317 billion, and its completion target shifted from 2026 to June 2028. The November incident has raised fresh concerns about whether further delays or additional financial liabilities now await.
Source: Engineering Review, 16–30 Nov 2026 (print), pp. 1, 4
Frequently Asked
Questions about this story
Was the main Tarbela Dam or its main tunnel damaged in the November 9 collapse?
No. WAPDA confirmed that the main Tarbela Dam and its critical structures were not under threat. The failure was confined to a rock section during excavation of the connecting tunnel; the main tunnel, powerhouse structure, tailrace culvert and switchyard showed no structural damage in the initial assessment.How much has the Tarbela T5 project cost risen after these construction failures?
The project's estimated cost rose from approximately Rs. 82 billion to Rs. 317 billion following the August 2025 cofferdam collapse. The November 2026 water ingress incident has raised further concerns about whether additional cost escalation may follow.When is the Tarbela T5 hydropower project now expected to be completed?
Following the August 2025 cofferdam collapse, the completion target was shifted from 2026 to June 2028. The November 2026 rock-collapse incident has raised fresh questions about whether that revised date can still be met.